In Western Australia, subdivision is decided by the WA Planning Commission (WAPC), not your local council. You apply to the WAPC on Form 1A, it consults the council and other agencies, and it approves, approves with conditions or refuses. Once the conditions are met, the WAPC endorses the final plan and Landgate issues the new titles.
This guide covers the application itself: the forms, the 2026-27 fees, the time each stage takes, and what to do if you need more time or disagree with a decision. For the rules that decide whether a block can be split, see our WA subdivision guide.
Before you apply
How do I apply to the WAPC for subdivision? Lodge a Form 1A application with the WA Planning Commission. The WAPC's preferred method is its Planning Online portal, and applications can also be posted. You need a subdivision plan based on an accurate, up-to-date feature survey, a current copy of the certificate of title and the landowner's consent. The fee is paid once lodgement has been verified.
In practice a licensed surveyor prepares the feature survey and the subdivision plan, and many owners also engage a town planner to check the lot sizes against the R-Codes and the local planning scheme before lodging.
The forms
| Form | What it is for |
|---|---|
| Form 1A | Application for approval of a freehold (green title) or survey-strata subdivision |
| Form 2A | Amended plans |
| Form 3A | Reconsideration of a decision |
| Form 4A | Extension of the approval period (s 145A) |
| Form 1C | Endorsement of the deposited plan or survey-strata plan |
All are on the WAPC's subdivision forms page. Strata and community titles have their own forms as well.
The fees from 1 July 2026
What is the WAPC subdivision fee in 2026-27? From 1 July 2026 the Form 1A fee for two lots up to and including 100 lots is $3,837 plus $85 per lot, which is $4,007 for a two-lot subdivision. Endorsement of the final plan on Form 1C is $719 plus $8 per lot. The WAPC says its fees are exempt from GST.
These are only the WAPC's fees. Council clearance fees, Landgate title fees and Water Corporation contributions come on top. Surveying and other professional work is an additional cost. Our WA subdivision cost guide adds up every government fee for a two-lot and a three-lot split.
How long the decision takes
How long does the WAPC take to decide a subdivision? The WAPC is to try to decide within 90 days after the plan is submitted, or a longer period agreed in writing with the applicant (Planning and Development Act 2005, s 143). Agencies it refers the plan to have 42 days to respond, or longer if the WAPC allows (s 142).
The WAPC can refer an application to the local council and to other agencies (s 142). Their comments can shape the conditions of approval.
If the period passes without a decision, the applicant can give the WAPC a written notice of default and then apply to the State Administrative Tribunal for a review as if the application had been refused (s 253). Our subdivision timeframe guide compares this with the other states.
If you disagree with the decision
If the WAPC refuses the application or imposes a condition you don't accept, you can ask it to reconsider on Form 3A, or apply to the State Administrative Tribunal for a review. The WAPC's guide says a tribunal review must be sought within 28 days of the date of the decision.
How long an approval lasts
How long is a WAPC subdivision approval valid? Three years from the date of approval for five lots or fewer, and four years for more than five lots (s 145A). The WAPC may grant one extension of two years on Form 4A. Its forms page says there is currently no fee for a Form 4A application.
The extension runs from the original expiry date, and only one extension is allowed. The WAPC decides each request under s 145A, so apply well before the approval lapses.
From conditions to new titles
Within the approval period you need to meet the conditions and lodge your plan for endorsement:
- Meet the conditions. Conditions vary by property and can include council and servicing agency requirements. They are cleared in consultation with the relevant council or agency.
- Lodge the plan for endorsement. Your surveyor prepares the deposited plan or survey-strata plan. Once the conditions are cleared, you apply to the WAPC on Form 1C for endorsement.
Applying for the new titles at Landgate follows endorsement.
A policy change to watch
On 24 October 2026 the WAPC released a draft Operational Policy Subdivision. It would take over parts of the current Operational Policy 2.2 Residential Subdivision, subject to the outcome of the review of the Residential Design Codes. The draft is not yet final.
Getting advice
A licensed surveyor prepares the plans and lodges the survey for endorsement, and a town planner can prepare and manage the application. If you'd like a first look at your own block before you engage them, you can check your block with Subdivision Checker.
Sources
- Subdivision application forms, guidelines and checklists (WA Planning Commission)
- WAPC Guide to subdivision applications and fees, version 10.7 (July 2026)
- Planning Online help (WA Department of Planning, Lands and Heritage)
- Planning and Development Act 2005 (WA)
- Draft Operational Policy Subdivision, 24 October 2026 (WA Planning Commission)
This guide is general information only, current at 23 November 2026. Fees change, usually on 1 July. Speak to a licensed surveyor or town planner about your property.