In the City of Joondalup, the lot size you need to subdivide comes from two places. The City's Local Planning Scheme No. 3 (LPS3) gives your lot a density code, and Table D of the state Residential Design Codes (R-Codes) sets the minimum and average site area for that code. The Western Australian Planning Commission (WAPC) makes the decision, not the City.

What sets Joondalup apart is its dual codes. Around train stations and centres, many lots carry a code such as R20/40, and the higher code only applies if the scheme's frontage criteria are met. The City also has its own crossover rules, a coastline under a long-term hazard plan, and Bush Forever sites. Figures are as at November 2026.

Which planning scheme applies in the City of Joondalup

The operative scheme is City of Joondalup Local Planning Scheme No. 3, gazetted on 23 October 2018. The Department of Planning, Lands and Heritage's current copy of the scheme text is updated to Amendment 21, gazetted 17 April 2026, and the department publishes it with 18 locality scheme maps, from Burns Beach to Warwick.

Clause 36 says "There are no special control areas which apply to this Scheme". Constraints such as bushfire and coastal hazard come from state policy and the City's other plans, covered below.

How to find your lot's R-Code

  • The City's online mapping tool. The City says it "can be used to identify the zoning and residential density (R-Code) of your property".
  • LPS3 scheme maps. The Kingsley locality map, for example, shows codes including R20, R20/40, R40 and R60, and its legend marks the "Area Subject to Clause 26 (7) ii of the Scheme Text".
  • Structure plans and activity centre plans for the areas listed below.
  • PlanWA. The department's statewide planning mapping tool.

The City's planning team can confirm the code for a specific lot.

Dual codes in the Housing Opportunity Areas

The City has 10 Housing Opportunity Areas: Sequoia Road/Telopia Drive to Warwick Grove Shopping Centre, Greenwood Village, the Sorrento laneway lots, Marmion Avenue to Greenwood Station, Whitfords Centre to Whitfords Station, Whitfords Station to Goollelal Drive, Belridge Centre to Edgewater Station, Edgewater Station to Trappers Drive, Heathridge, and Currambine Station. Lots in these areas carry dual codes, and the City says the higher code can only be used where the requirements of LPS3 clause 26 and the Residential Development Local Planning Policy are met.

The rules are in clause 26 of LPS3, introduced by Amendment 5 (gazetted 29 January 2021):

  • Clause 26(4): where a dual density code applies, "the base R20 density code shall apply", unless the higher code is found acceptable having regard to clauses 26(5) and 26(7)i.
  • Clause 26(5): the higher code may be applied to single and grouped dwellings with a minimum frontage of 9 m at the primary street setback, or to grouped dwellings on corner lots with frontages to two streets and rear common property access, with a minimum frontage of 6 m.
  • Clause 26(7)(i): multiple dwellings (apartments) need a minimum site width of 20 m at the street boundary.
  • Clause 26(7)(ii): in R20/40 areas, multiple dwellings must meet the average site area per dwelling for a single or grouped dwelling at that code. That is 220 m² at R40, rather than the 115 m² Table D allows for multiple dwellings. This does not apply where the site fronts a Local Distributor Road or Other Regional Road, or is within the mapped 800 m walkable catchment of a strategic, secondary or specialised activity centre or high-frequency railway station, or 400 m of a district activity centre.

The City says conditions on higher-code development may cover verge landscaping and street tree zones, common property landscaping and lighting, and crossover location and design. A licensed surveyor or town planner can advise how the frontage criteria apply to a particular layout.

Lot sizes for common Joondalup codes

These figures are from Table D of the R-Codes Volume 1 (Version 3, 10 April 2026) for single houses and grouped dwellings.

R-Code Minimum site area (m²) Average site area (m²) Rear battle-axe minimum (m²)* Minimum frontage (m)*
R20 350 450 450 10
R25 300 350 425 8
R30 260 300 410 –
R40 180 220 380 –
R60 120 150 120 –

*Table D applies these two columns to single houses only. A dash means not applicable.

Both tests apply. On an R20/40 lot assessed at the base R20 code, two lots generally need at least 900 m² between them. If the higher R40 code is accepted, the figure is 440 m², but the clause 26(5) frontage criteria (9 m, or 6 m for grouped dwellings on corner lots) still apply. For the full table and the five per cent variation, see the minimum lot size for subdivision in WA. For rear lots, see battle-axe subdivision explained.

Structure plan and activity centre areas

The department lists structure plans for Burns Beach, the Currambine District Centre, Hillarys, Iluka and the Whitford Activity Centre, and activity centre plans for the Joondalup Activity Centre and Sorrento. The City says structure plans coordinate "zoning, subdivision and development", and local development plans can add built form controls.

Several recent amendments rezoned former school and other sites with new codes, for example the Greenwood Local Structure Plan area (Amendment 17, 14 February 2025), which applied R40, R60 and R80. Check the documents for your street.

Two other scheme rules are worth knowing:

  • Large lots. Table 6 says that for lots of one hectare or larger with a code above R20, "the minimum residential density to be achieved is 25 dwellings per site hectare".
  • Restrictive covenants. Clause 35 says a covenant that limits the number of dwellings is extinguished or varied to the extent it allows fewer dwellings than the scheme. Development approval is then needed for any dwelling above the covenant's limit, and the application must be advertised.

Local planning policies

In a notice dated 16 January 2026, the City announced a new Residential Development Local Planning Policy – 2025, adopted at the 5 December 2025 Council meeting. The City says the policy replaces or modifies some R-Code provisions. The same notice revoked the Development in Housing Opportunity Areas policy, the 2021 Residential Development policy, and the Subdivision and Dwelling Development Adjoining Areas of Public Open Space policy. Ask the City for the current policy text that applies to your lot.

Crossovers and street trees

The City's verges and crossovers page says:

  • A maximum of two crossovers is permitted, provided their combined width is no wider than 9 m, with a clear separation between them. A single crossover can be up to 6 m wide.
  • Only grey pre-mix concrete is permitted, and where a footpath exists it must run continuously through the crossover. Designs that depart from the Crossover Guidelines need approval from Planning Services.
  • A one-off $375 subsidy is available for the first crossover, applied for within six months of construction. The City will not subsidise a second crossover on the same lot.

Street trees are maintained by the City. These rules matter for layouts that need a second driveway.

Heritage

The City's Heritage List is a smaller list of the most significant places from its Local Heritage Survey, and gives them protection under LPS3. The City says owners who want to demolish, alter or develop a listed place need development approval. The current Local Heritage Survey was endorsed on 28 May 2024 and has no statutory effect on its own.

The coast, bushland and bushfire

  • Coast. The City's 17 km coastline runs from Marmion to Burns Beach. Its Coastal Hazard Risk Management and Adaptation Plan, required under State Planning Policy 2.6, is still in development, with completion listed for 2027.
  • Bush Forever. The City's Local Planning Strategy (endorsed by the WAPC on 10 November 2017) says there are seven Bush Forever sites in the City, totalling about 234 ha of native vegetation.
  • Bushfire. Check the DFES Map of Bush Fire Prone Areas, whose current version took effect on 13 December 2025. Designation can trigger State Planning Policy 3.7 where a proposal increases development intensity.

How subdivision approval works

You apply to the WAPC. The City's subdivision fact sheet says the City comments on applications and recommends conditions, and that it "is unable to provide advice on the design of a subdivision". The City and agencies such as Water Corporation have 42 days to respond, and the WAPC is to decide within 90 days unless otherwise agreed. Approval is valid for 3 years for 5 lots or fewer, or 4 years for 6 or more.

Once all the works are complete, you lodge a clearance request with the City, with its Subdivision Clearance Checklist and a copy of the deposited or survey-strata plan. The property is inspected, and if the conditions are met the City issues a clearance letter with an endorsed plan.

From 1 July 2026 the WAPC application fee for a freehold subdivision of two to 100 lots is $3,837 plus $85 per lot, and endorsement is $719 plus $8 per lot. Water Corporation's standard infrastructure contributions for 1 July 2026 to 30 June 2027 are $2,756 for water and $5,121 for wastewater per lot, plus $41 for drainage in urban declared drainage areas. They are not subject to GST. See how to subdivide land in Western Australia for each step, and our subdivision cost calculator for a broader estimate.

For how neighbouring councils differ, see our guides to the City of Stirling and the City of Wanneroo.

Changes on the way (proposed, not in force)

  • Draft R-Codes. Released on 24 October 2026, they propose scrapping average lot sizes for R10 to R25 in Perth and Peel. Submissions close at 5.00pm (AWST) on Friday 26 February 2027, and the department expects amendments to begin coming into effect later in 2027. Applications continue to be assessed under the current framework.
  • Building Sustainable Neighbourhoods. The City's review of where infill housing should go is at Phase 3 (strategic options), with round 2 consultation closed. The outcome feeds a new Local Planning Strategy that needs WAPC and Minister for Planning approval.

Contacting the City of Joondalup

The City can be reached on (08) 9400 4000 or info@joondalup.wa.gov.au. Its administration centre is at 90 Boas Avenue, Joondalup WA 6027, and its postal address is PO Box 21, Joondalup WA 6919.

Check your own block

A Subdivision Checker report applies these rules to one address: planning and zoning, heritage, environment, contamination, bushfire, flood, servicing and access, measured lot geometry and concept subdivision design options, plus indicative cost ranges labelled as estimates. It is a starting point, not a substitute for advice from a licensed surveyor or town planner. To see how the checks are set out, view our sample report, or order a report for your address.

Frequently asked questions

What is the minimum lot size for subdivision in Joondalup?

It depends on the density code (R-Code) that Local Planning Scheme No. 3 gives your lot. Table D of the R-Codes Volume 1 then sets the minimum and average site area. At R20 the minimum is 350 m² and the average is 450 m², so two lots generally need at least 900 m². At R40 it is 180 m² and 220 m². In Joondalup's dual-coded areas, such as R20/40, the R20 figures apply unless the higher code is found acceptable under the scheme's criteria.

How does a dual code like R20/40 work in Joondalup?

Under clause 26(4) of Local Planning Scheme No. 3, the base R20 code applies unless the higher code is found acceptable having regard to the scheme's criteria. Clause 26(5) says the higher code may be applied to single and grouped dwellings with a minimum frontage of 9 m at the primary street setback, or to grouped dwellings on corner lots with frontages to two streets and rear common property access, with a minimum frontage of 6 m.

Can I subdivide in Joondalup?

It depends on your lot's zoning, its R-Code, whether it meets the Table D site areas and, in dual-coded areas, whether the higher code criteria are met. Access, crossovers, servicing, bushfire and coastal matters can also affect the answer. The Western Australian Planning Commission (WAPC) decides, and a licensed surveyor or town planner can advise on a specific lot.

Does the City of Joondalup approve subdivisions?

No. The WAPC is the determining authority. The City's fact sheet says it comments on applications and recommends conditions, and that it is unable to provide advice on the design of a subdivision. After the works are done, you apply to the City for clearance of its conditions, and the property is inspected before a clearance letter is issued.

How many crossovers can I have on a Joondalup lot?

The City's verges and crossovers page says a maximum of two crossovers is permitted, provided their combined width is no wider than 9 m, and a single crossover can be up to 6 m wide. The City's one-off $375 subsidy is for a property's first crossover (or replacing an old bitumen one) built to its guidelines. It does not cover a second crossover on the same lot.

Are lot sizes in Joondalup changing?

Changes are proposed but not in force. The draft R-Codes released on 24 October 2026 propose scrapping average lot sizes for R10 to R25 in Perth and Peel, with comment closing at 5.00pm (AWST) on Friday 26 February 2027. Separately, the City's Building Sustainable Neighbourhoods review of infill housing is still at the strategic options stage.

Sources

This guide is general information only, current at November 2026. Rules, fees and maps change, and every block is different. Speak to a licensed surveyor or town planner about your property.

More subdivision guides

See what applies to your block.

A Subdivision Checker report works through the lot size test, constraints, approval pathway and costs for your address, with every source listed. Full report $199, or a $39 Snapshot.