Can I subdivide my block in Victoria? Often you can, but whether you can subdivide land in Victoria depends on three things: the zone and its schedule in your council's planning scheme, the overlays mapped over your block, and what is registered on your title.
Victoria also works differently from most states. Subdivision runs under two Acts and two approvals: a planning permit under the Planning and Environment Act 1987, then certification of the plan under the Subdivision Act 1988. Your new titles only exist once Land Services Victoria registers the plan.
This guide covers who decides, the rules for splitting a block, the steps, timeframes, 2026-27 fees and the common complications.
Who approves a subdivision in Victoria
In Victoria your local council handles both approvals. As the responsible authority under the planning scheme, it decides the planning permit. Under the Subdivision Act 1988 it then certifies the plan of subdivision and, at the end, issues the statement of compliance.
Other bodies come in as referral authorities under Clause 66. A determining referral authority's objections and conditions bind the council; a recommending one's advice must be considered. Under a flood overlay, Melbourne Water is determining inside its waterway management district, and the floodplain management authority is recommending outside it. For a subdivision in the Bushfire Management Overlay, the relevant fire authority is recommending.
Under section 8 of the Subdivision Act the council also refers the plan to servicing authorities such as the water corporation. If you disagree with the council's decision, or it does not decide in time, you can apply to the Victorian Civil and Administrative Tribunal (VCAT).
The Registrar of Titles at Land Services Victoria registers the plan and issues the new titles. Land Use Victoria became Land Services Victoria on 21 May 2026.
The rules that decide whether your block can be split
Zone and minimum lot size
Victoria has no single statewide minimum lot size. Each zone clause sets its own approach, and your council's schedule may add to it. Your zone and overlays appear in the planning property report for your address, downloadable from VicPlan.
| Zone | Minimum lot size rule |
|---|---|
| General Residential Zone (Clause 32.08) | No minimum lot size in the zone clause. A vacant lot under 400 m² must contain at least 25% garden area |
| Neighbourhood Residential Zone (Clause 32.09) | The schedule may specify a minimum lot size. The same 25% garden area rule applies to vacant lots under 400 m² |
| Residential Growth Zone (Clause 32.07) | No minimum lot size in the zone clause |
| Low Density Residential Zone (Clause 32.03) | The area in the schedule. Where none is specified, 0.4 hectare per lot without reticulated sewerage, or 0.2 hectare with it |
In the General and Neighbourhood Residential Zones the 400 m² figure is not a minimum lot size. It only means a vacant lot drawn under 400 m² must show at least 25% garden area. A lot that keeps the existing house is not a vacant lot. Rural zones and the Urban Growth Zone have their own rules, so read your zone clause and schedule.
Clause 56: residential subdivision standards
Clause 56 (Residential Subdivision) sets objectives and standards. An application must meet all the objectives the zone specifies and should meet the standards. In the residential zones, even a two-lot subdivision must address Clauses 56.04-2 (lot area and building envelopes), 56.04-5 (common area), 56.06-8 (lot access) and 56.07-4 (stormwater management), plus 56.03-5 if the land is in a Neighbourhood Character Overlay. A subdivision of 3 to 15 lots picks up most of Clause 56.
Frontage, access and battle-axe lots
Access to a rear (battle-axe) lot is assessed against the lot access objective in Clause 56.06-8. Its standard says the design and construction of a crossover should meet the requirements of the relevant road authority.
The existing house, two dwellings and VicSmart
Many owners keep the existing house and create one new lot; others first get a permit for two dwellings. Since Amendment VC288 (16 October 2025), the residential zone clauses, such as the General Residential Zone, include these VicSmart subdivision classes:
- a two-lot subdivision where a permit for up to two dwellings has been issued and has not expired, and each lot will contain one existing or permitted dwelling
- a two-lot subdivision for residential development that creates at least one vacant lot, provided the land is not in an Environmental Audit Overlay, a Neighbourhood Character Overlay or a designated bushfire prone area, and does not contain native vegetation if it is 0.4 hectare or more
- lots that each contain an existing building or car space built lawfully, with an occupancy permit or certificate of final inspection issued within five years
- a boundary realignment that reduces neither lot by 15% or more
The Low Density Residential Zone is excluded from the two-dwelling class. A permit cannot be granted to create a separate lot for land containing a small second dwelling, so a granny-flat-style small second dwelling cannot later be split off onto its own title.
Step by step: the subdivision process in Victoria
- Check feasibility. Download the planning property report for your address, read your zone and overlay clauses, and get a current copy of your title to check for covenants, section 173 agreements and easements.
- Engage a licensed land surveyor (and a town planner if needed) to prepare the plan of subdivision.
- Apply for the planning permit, through SPEAR (the state's online subdivision system) or the council's portal. The council may ask for more information, refer the application, and require notice to neighbours unless it is VicSmart or exempt.
- Receive the decision. The council issues a permit, a notice of decision to grant, or a refusal. Permits usually carry conditions.
- Certification. The surveyor lodges the plan for certification under section 5 of the Subdivision Act. The council refers it to servicing authorities under section 8. If a referral authority does not reply within the prescribed time, it is taken to have consented.
- Meet the conditions. Build any required works (sewer, water, drainage, crossovers), pay contributions, and obtain each servicing authority's written consent.
- Statement of compliance. Under section 21 of the Subdivision Act, the council issues the statement of compliance once the requirements have been met or secured.
- Registration and new titles. The certified plan and statement of compliance are lodged with Land Services Victoria, which accesses the plan through SPEAR and issues the new titles.
Validity: a subdivision permit generally lapses if the plan is not certified within two years of the permit being issued. A certified plan expires if it is not registered within five years of certification. Always check the expiry conditions on your own permit.
How long it takes
The prescribed time for the council to decide a standard planning permit application is 60 days. For a VicSmart application it is 10 business days. If the council asks for more information within the prescribed period (28 days for a standard application), the clock stops until you respond. If the council does not decide within the prescribed time, you can apply to VCAT under section 79 of the Planning and Environment Act for a review of its failure to grant a permit.
Notice, objections, referrals and any VCAT review add time. After the permit, certification, works and service authority consents usually take longest, and no official average exists.
What it costs
Statutory fees (2026-27)
Victorian planning fees are set in fee units. For 2026-27 the fee unit is $17.27, applying from 1 July 2026. Planning Victoria lists these fees under the Planning and Environment (Fees) Regulations 2016 and Subdivision (Fees) Regulations 2016:
- Planning permit to subdivide land into 2 lots (Class 18): $1,537.00 (89 fee units)
- Any other subdivision (Class 20): $1,537.00 per 100 lots created
- Subdivide an existing building (Class 17) or realign a boundary / consolidate (Class 19): $1,537.00 each
- VicSmart application to subdivide or consolidate (Class 9): $233.10 (13.5 fee units)
- Permit to create, vary or remove an easement or restriction (Class 21): $1,537.00
- Certification of the plan and issue of the statement of compliance: $203.80 (11.8 fee units)
- Council checking of engineering plans: up to 0.75% of the estimated cost of works; supervision of works: up to 2.5%
Land Services Victoria's registration fee depends on the plan, and you work it out with its subdivision fee calculator (fees from 1 July 2026). These figures are current at October 2026 and change every year.
Other costs
Totals vary widely from block to block. Expect some or all of these cost categories:
- Surveyor and town planner: survey, plan of subdivision and, if needed, planning reports.
- Service connections and works: water, sewer, drainage, electricity, gas, telecommunications and vehicle crossings.
- Water corporation contributions: charged per new lot. As one example, Yarra Valley Water's 2026-27 standard-region New Customer Contribution is $1,113.63 for water and $1,113.63 for sewer per lot. Your water corporation sets its own rates.
- Drainage: Melbourne Water's pre-development advice is free and covers flood information and any Development Services Scheme contribution.
- Public open space: the amount in your council's schedule to Clause 53.01, or up to 5% of site value under section 18 of the Subdivision Act where the schedule sets none. Two-lot subdivisions are exempt where the council considers further subdivision of each lot unlikely.
- Growth Areas Infrastructure Contribution (GAIC): only on land brought inside the urban growth boundary since 2005. Subdivision of the land is one of its triggering events.
- Specialist reports, legal fees, demolition and public notice, where needed.
Things that can stop or complicate a subdivision
State heritage. Heritage Victoria manages the Victorian Heritage Register and the Victorian Heritage Inventory of historical archaeological sites. If a place is on the Register, you must obtain approval from Heritage Victoria as well as dealing with the council.
Local heritage. The Heritage Overlay (Clause 43.01) requires a permit to subdivide land. That includes subdividing a heritage place on the Victorian Heritage Register.
Aboriginal cultural heritage. Under the Aboriginal Heritage Act 2006, a cultural heritage management plan (CHMP) is required where a high impact activity is in an area of cultural heritage sensitivity. Subdivision into three or more lots can be a high impact activity, and some small subdivisions are exempt. The council cannot issue the permit until it receives the approved CHMP. The sensitivity mapping is on ACHRIS and in the planning property report.
Bushfire. The Bushfire Management Overlay (Clause 44.06) requires a permit to subdivide, and the application must meet Clause 53.02 unless it meets the requirements in a schedule to the overlay. A designated bushfire prone area under section 192A of the Building Act 1993 is a separate building control. It also rules out the vacant-lot VicSmart class.
Flood. The Land Subject to Inundation Overlay (Clause 44.04) requires a permit to subdivide. The Floodway Overlay, Special Building Overlay and Urban Floodway Zone are referred to Melbourne Water or the floodplain management authority under Clause 66.03.
Native vegetation and trees. Clause 52.17 requires a permit to remove, destroy or lop native vegetation, unless an exemption applies.
Contamination. Under the Environmental Audit Overlay (Clause 45.03), a sensitive use such as a dwelling needs a preliminary risk screen assessment statement or environmental audit statement first. Victoria Unearthed is a state interactive map for investigating potential contamination of land and groundwater.
Easements, sewer and water capacity. Servicing authority requirements can mean new easements or extended mains. Ask your water corporation early about capacity.
Covenants and section 173 agreements. A section 173 agreement is recorded on title, binds future owners and can prohibit or restrict development. Removing or varying a restrictive covenant under section 23 of the Subdivision Act needs a permit under Clause 52.02.
Existing buildings and common property. Subdividing existing buildings or creating a shared driveway as common property adds building compliance and an owners corporation.
A quick checklist for your block
- What zone and schedule apply, and does the schedule set a minimum lot size?
- Would any vacant lot be under 400 m², and could it show 25% garden area?
- Which overlays appear on the planning property report: heritage, bushfire, flood, environmental audit, vegetation?
- Is the block in a designated bushfire prone area or an area of Aboriginal cultural heritage sensitivity?
- Does your title show a covenant, section 173 agreement or easement?
- Can a rear lot get practical vehicle access and its own crossover?
- Are sewer, water and drainage available, and who is your water corporation?
- Could the proposal fit a VicSmart class?
Where a Subdivision Checker report fits
A Subdivision Checker report brings together the planning rules, mapping and records for one address in Victoria in one professional report: planning and zoning, including the minimum lot size rules that apply, heritage, environment, bushfire, flood, servicing, contamination and title, plus indicative costs. It is a starting point that helps you understand your block and know what to ask a licensed surveyor or town planner. It is not a substitute for their advice. Order a report for your address.
Guides for other states and territories are at our guides page.
Frequently asked questions
Is there a minimum lot size for subdivision in Victoria?
It depends on the zone. The General Residential and Residential Growth Zones set no minimum lot size in the zone clause. In the Neighbourhood Residential Zone a schedule may set one. In the Low Density Residential Zone each lot must meet the schedule area, or 0.4 hectare without reticulated sewerage and 0.2 hectare with it where none is specified. Rural zones set their own areas.
Can a two-lot subdivision go through VicSmart?
Often, yes. Since Amendment VC288 in October 2025, the residential zone clauses include VicSmart classes for two-lot subdivisions, including one that creates a vacant lot. That class does not apply if the land is in an Environmental Audit Overlay, a Neighbourhood Character Overlay or a designated bushfire prone area. VicSmart applications have a 10 business day prescribed time and the fee is $233.10 in 2026-27.
How much is the council planning permit fee to subdivide in Victoria?
For 2026-27 the statutory fee to subdivide land into two lots is $1,537.00, which is 89 fee units at $17.27. Other subdivisions are $1,537.00 per 100 lots created, and a VicSmart subdivision is $233.10. Certification of the plan and the statement of compliance together cost $203.80. Fees are set in fee units and change every 1 July.
When do the new titles actually exist?
Not when the permit is issued and not when the plan is certified. After the council issues a statement of compliance, the certified plan is lodged with Land Services Victoria, the Registrar of Titles, for registration. Land Services Victoria then issues the new titles for the lots. The registration fee is worked out with its subdivision fee calculator.
Do I have to pay a public open space contribution?
Usually, unless an exemption applies. Clause 53.01 requires a contribution set in your council's schedule. Where the schedule sets no amount, the council may still require up to five per cent under section 18 of the Subdivision Act 1988. A two-lot subdivision is exempt where the council considers it unlikely that each lot will be further subdivided.
Sources
- Planning and Environment Act 1987 (Vic)
- Subdivision Act 1988 (Vic)
- Planning Victoria – Fees (2026-2027)
- Planning Victoria – Subdivision fees (2026-2027)
- Department of Treasury and Finance – Indexation of fees and penalties (fee unit 2026-27)
- Planning Victoria – Faster approvals for two homes on a lot and subdivisions (Amendment VC288)
- Victoria Planning Provisions – Clause 32.08 General Residential Zone
- Victoria Planning Provisions – Clause 32.09 Neighbourhood Residential Zone
- Victoria Planning Provisions – Clause 32.07 Residential Growth Zone
- Victoria Planning Provisions – Clause 32.03 Low Density Residential Zone
- Victoria Planning Provisions – Clause 56 Residential Subdivision
- Victoria Planning Provisions – Clause 59.11 Two Lot Residential Subdivision
- Victoria Planning Provisions – Clause 53.01 Public Open Space Contribution
- Victoria Planning Provisions – Clause 66.03 Referral of permit applications
- Victoria Planning Provisions – Clause 43.01 Heritage Overlay
- Victoria Planning Provisions – Clause 44.06 Bushfire Management Overlay
- Victoria Planning Provisions – Clause 44.04 Land Subject to Inundation Overlay
- Victoria Planning Provisions – Clause 45.03 Environmental Audit Overlay
- Victoria Planning Provisions – Clause 52.17 Native vegetation
- Victoria Planning Provisions – Clause 52.02 Easements, restrictions and reserves
- Planning Victoria – Subdivision Act User Guide (November 2012)
- Planning Victoria – Planning Permits chapter (prescribed times)
- Planning Victoria – Guide to Victoria's planning system: Agreements
- Planning Victoria – Planning property report
- Planning Victoria – Local heritage protection
- Planning Victoria – PPN45: Aboriginal Heritage Act 2006 and the planning permit process
- First Peoples – State Relations – How to consider cultural heritage in your proposed development
- VCAT – Review of a planning decision by a permit applicant
- SPEAR – How SPEAR works
- Land Services Victoria – Customer Information Bulletin 241
- Land Services Victoria – 2026-27 fees
- State Revenue Office – Growth areas infrastructure contribution
- Yarra Valley Water – New customer contributions
- Melbourne Water – Pre-development advice
- Victoria Unearthed
- City of Knox – Subdivision
- Corangamite Shire – Planning information: Subdivision process
This guide is general information only, current at October 2026. Rules, fees and maps change, and every block is different. Speak to a licensed surveyor or town planner about your property.