"How long will it take?" is one of the first questions anyone asks about a subdivision. Nobody can promise a date, but the law in every state and territory sets a period within which the authority should decide the application. Knowing that period, what stops the clock and what you can do if it runs out gives you a realistic starting point.
This guide sets out those legal time limits. It does not predict how long your application will take. Real timeframes depend on the site, referrals to other agencies, requests for more information, and how quickly the applicant and their consultants respond.
The decision periods at a glance
| State | Who decides | Time the law sets | If no decision in time |
|---|---|---|---|
| WA | WA Planning Commission | 90 days, or longer if agreed in writing | Applicant can give notice; treated as refused; review at the State Administrative Tribunal |
| NSW | Council or local planning panel | 40 days (60 days for integrated, designated or concurrence development) | Treated as refused; appeal to the Land and Environment Court |
| VIC | Council | 60 days, weekends and public holidays included (VicSmart: 10 business days) | Applicant can ask VCAT to review the failure to decide |
| QLD | Council (assessment manager) | 35 business days for the decision stage (after any information request, referral and public notification stages) | Code assessable: applicant can give a deemed approval notice. Impact assessable: no deemed approval |
| SA | Assessment manager or assessment panel | 30 business days for 10 or fewer allotments with no new public road; 60 business days otherwise | No deemed consent for land division |
| TAS | Council | 42 days for a discretionary application; 28 days for a permitted one | Deemed permit, with conditions set by the tribunal |
| ACT | Territory Planning Authority | 30 working days; 45 if there are representations; 60 for significant development | Treated as refused for review at ACAT |
| NT | Development Consent Authority | No fixed period ("as soon as practicable") | Applicant can seek a review at NTCAT if no decision within 84 days |
Business days and working days leave out weekends and public holidays. Where the law simply says "days", the table does too.
What pauses or restarts the clock
The decision period rarely runs straight through. The most common reasons it stops are:
- Requests for more information. In most states the period stops while the authority waits for information it has asked for, if it asks within the time the law allows. In NSW the period stops if the council asks within 25 days of lodgement. In Victoria the 60 days start again from the day the information is given.
- Public notice. In Victoria the clock stops from when council requires notice to be given until the last notice is given, then carries on from where it stopped. Other states build notification into the period or add time for it.
- Referrals. In WA, agencies the Commission refers the plan to have 42 days to comment. In South Australia, extra time is added in some cases, for example when the planning consent needs public notification or referral to another agency.
- Stopping the clock by choice. In Queensland the applicant can stop the clock for up to 130 business days in total over the application.
So a 35-business-day or 90-day period on paper can stretch well beyond that in practice, without anyone breaking the rules.
What happens after approval
The decision period only covers the approval. Before new titles issue, most subdivisions still need to:
- meet the conditions of approval, such as connecting water, sewer and power, building crossovers or paying contributions
- have a licensed surveyor prepare the final survey plan
- have the plan endorsed, certified or sealed by the authority
- lodge the plan with the land titles office
These steps have few fixed time limits and depend mostly on the applicant, their consultants and the service providers. Approvals also expire if they are not acted on:
- WA: the survey plan must be lodged for endorsement within 3 years of approval, or 4 years for a plan creating more than 5 lots, with one 2-year extension available.
- QLD: the plan of subdivision must be given to the council within 4 years after the approval takes effect, unless the approval says otherwise.
- SA: a land division approval generally lapses 2 years after it takes effect. It runs to 3 years if, within those 2 years, work has substantially started or an application for the land division certificate has been lodged with the State Planning Commission.
State by state
Western Australia
Subdivision in WA is decided by the WA Planning Commission, not your council. Under the Planning and Development Act 2005, the Commission is to try to deal with a plan of subdivision within 90 days after it is submitted, or a longer period agreed in writing (s 143). Agencies it refers the plan to have 42 days to respond (s 142). If the period passes without a decision, the applicant can serve a written notice of default and the application is then treated as refused, which can be reviewed at the State Administrative Tribunal (s 253). Our WA subdivision guide covers the full process.
New South Wales
Under the Environmental Planning and Assessment Regulation 2021, a council is taken to have refused a development application if it hasn't decided it within the assessment period: 40 days for most applications, and 60 days for integrated, designated or concurrence development (cl 91). The period starts on the day the application is lodged (cl 92). The Land and Environment Court says an appeal is generally to be made within 6 months. See our NSW subdivision guide.
Victoria
The Victorian Government's guide to the planning system says the prescribed time for council to decide most planning permit applications is 60 days, with weekends and public holidays included, and 10 business days for VicSmart applications. If council asks for more information, the period starts again from the day it is given. Once the period has passed, the applicant can apply to VCAT for a review of the failure to decide. See our Victorian subdivision guide.
Queensland
Queensland's Development Assessment Rules give the assessment manager a decision period of 35 business days, which starts once the earlier information request, referral and public notification stages are finished. Many reconfiguring a lot applications are code assessable, but the local planning scheme sets the category for each site. If a code assessable application isn't decided in time, the applicant can give a deemed approval notice under the Planning Act 2016 (s 64). Impact assessable applications don't get deemed approval. See our Queensland subdivision guide.
South Australia
Under the Planning, Development and Infrastructure (General) Regulations 2017, a land division of 10 or fewer allotments with no new public road is to be decided within 30 business days, and other land divisions within 60 business days (reg 53). Where the application also needs planning consent, extra time is added to that assessment for public notification and referrals to other agencies. PlanSA's guide to development assessment confirms there is no deemed consent for land division. See our South Australian subdivision guide.
Tasmania
Under the Land Use Planning and Approvals Act 1993, council has 42 days to decide a discretionary application, including the advertising period, and 28 days for a permitted one. If it asks for more information, the period stops until the information is provided (s 54). If council doesn't decide in time, it is taken to have granted a permit, on conditions set by the tribunal (s 59). See our Tasmanian subdivision guide.
Australian Capital Territory
Under the Planning Act 2023, the Territory Planning Authority has 30 working days to decide a development application if no representations are made, 45 working days if they are, and 60 working days for significant development (s 192). Since 10 November 2026, when the main provisions of the Planning (Missing Middle Housing) Amendment Act 2026 commenced, a subdivision is significant development only if it also creates or removes roads (s 42A), so a typical residential block split falls under the 30 or 45 working day periods. A further information request pauses the period. If no decision is made in time, the application is taken to be refused so the applicant can seek a review at ACAT (s 193). See our ACT subdivision guide.
Northern Territory
The Planning Act 1999 sets no fixed decision period: the Development Consent Authority is to decide an application as soon as practicable after considering it (s 53). If no decision has been made within 84 days of applying, the applicant can seek a review at the NT Civil and Administrative Tribunal (s 112). See our NT subdivision guide.
Frequently asked questions
How long does subdivision approval take in WA?
The Western Australian Planning Commission is to try to decide a plan of subdivision within 90 days after it is submitted, or a longer period agreed in writing. Agencies it refers the plan to have 42 days to comment. If no decision is made in time, the applicant can give written notice and the application is treated as refused, which opens a review at the State Administrative Tribunal.
What happens if a council doesn't decide a subdivision application in time?
It depends on the state. In WA (after the applicant gives notice), NSW, the ACT and the NT the application can be treated as refused so the applicant can seek a review or appeal. In Queensland, a code assessable application can be deemed approved, and in Tasmania the council is taken to have granted a permit, on conditions set by the tribunal. In South Australia there is no deemed consent for land division.
Does the clock stop when the council asks for more information?
In most states, yes, if the request is made within the time the law allows. A request for further information pauses or restarts the assessment period, so the time the applicant takes to respond is not counted. In Victoria the 60-day period starts again from the day the information is given.
Is the decision period the whole subdivision timeframe?
No. The decision period only covers the approval decision. After approval, conditions usually have to be met, works built, a survey plan prepared and the plan endorsed or sealed before new titles issue, and those steps depend mostly on the applicant and their consultants.
Getting a realistic timeframe
A local town planner or licensed surveyor can tell you which referrals your block is likely to trigger, which conditions are common in your area and how long those steps usually take. Our guides to what a surveyor does and what subdivision costs cover the other side of the plan.
To see what applies to your block, and what to raise with your planner or surveyor, check your block with Subdivision Checker.
Sources
- Planning and Development Act 2005 (WA), ss 142, 143, 145A, 253
- Environmental Planning and Assessment Regulation 2021 (NSW), cl 91-94, as made
- Development application appeals (Land and Environment Court of NSW)
- Guide to Victoria's planning system, Planning permits, 3.4.4 When must a decision be made? (Victorian Government)
- DA Rules guidance, version 3 (Queensland Government)
- Planning Act 2016 (Qld), ss 64, 85
- Planning, Development and Infrastructure (General) Regulations 2017 (SA), reg 53
- Guide to development assessment under the PDI Act (PlanSA)
- Land Use Planning and Approvals Act 1993 (Tas), ss 54, 57-59
- Permits, Tasmanian Planning Scheme (State Planning Office)
- Planning Act 2023 (ACT), ss 42A, 192-193
- After you apply, development applications (ACT Planning)
- Planning Act 1999 (NT), ss 53, 112, 114
This guide is general information only, current at November 2026. Time limits can change, so check the current legislation or speak with a town planner or licensed surveyor in your state.