Subdivision cost in WA: the 2026-27 government fees

Every government fee for a small Western Australian subdivision from 1 July 2026, added up for a two-lot and a three-lot split, plus the costs that are quoted rather than set.

Updated 6 min read

Want the answer for your address? Your report checks the zoning, lot size, constraints and costs for your block, in your inbox within 1–2 hours.

Check my block

Subdividing a block in Western Australia involves two kinds of cost: fees set by government and Water Corporation, which are published, and work priced by your surveyor, planner, engineer and contractors, which is quoted for your site. This guide sets out every published fee for a small subdivision from 1 July 2026 and adds them up for a two-lot and a three-lot split.

For a two-lot green-title or survey-strata split, the published fees and Water Corporation contributions come to $13,564.50, assuming the council charges the maximum clearance fee, the existing lot is already connected to water and sewer, and Water Corporation contributions are charged on the extra lot only. The quoted work usually costs much more than this, and depends heavily on the block.

The government fees, step by step

1. WAPC application

In WA the Western Australian Planning Commission (WAPC), not the council, decides subdivision applications. From 1 July 2026, under the Planning and Development (Fees) Amendment Notice 2026, the fee for a freehold, survey-strata or community titles subdivision of 100 lots or fewer (Form 1A) is $3,837 plus $85 per lot. Survey-strata has no separate fee; it falls under the same item.

If the plan has to change during assessment, an amended plan (Form 2A) is $1,398 plus $28 per lot. Asking the WAPC to reconsider a refusal or a condition (Form 3A) is $1,579 plus $34 per lot.

2. Council clearance

Once approved, each condition must be cleared by the agency named in that condition. The council's clearance fee is capped by Schedule 2 of the Planning and Development Regulations 2009: a maximum of $73 per lot where no more than five lots are created. Councils can charge less.

3. WAPC endorsement

When the conditions are cleared, the WAPC endorses the deposited or survey-strata plan (Form 1C): $719 plus $8 per lot.

4. Landgate lodgement and new titles

Landgate registers the plan and issues the new titles. From 1 July 2026 (no GST):

  • deposited plan or strata/survey-strata plan lodgement: $364 plus $97 per lot
  • application for new titles on a deposited plan: $225.10 plus $8.20 per lot
  • a copy of the certificate of title (title search): $33.90 per title

5. Water Corporation infrastructure contributions

For 1 July 2026 to 30 June 2027, Water Corporation's infrastructure contributions are $2,756 for water and $5,121 for wastewater per lot, plus $41 for drainage on green-title lots in urban declared drainage areas of metropolitan Perth (drainage contributions do not apply to strata subdivisions). Contributions are payable when a subdivision creates extra lots that need Water Corporation's services. The totals below assume the existing lot is already connected and only the extra lots are charged. Infrastructure contributions are not subject to GST, and in some circumstances they may be deferred. Water Corporation confirms the amount for your subdivision, and any main extension your lots need is extra work, quoted separately. Its Small developments handbook explains the subdivision process and its requirements.

What the fees add up to

The table below adds up the published fees for a split of one connected lot into two and into three lots, with the maximum council clearance fee and water and wastewater contributions charged on the extra lots only. It leaves out the drainage charge, which applies only in some areas, and everything that is quoted.

Fee (from 1 July 2026) Two lots Three lots
WAPC application ($3,837 + $85 per lot) $4,007.00 $4,092.00
Council clearance (up to $73 per lot) $146.00 $219.00
WAPC endorsement ($719 + $8 per lot) $735.00 $743.00
Landgate plan lodgement ($364 + $97 per lot) $558.00 $655.00
Landgate new titles ($225.10 + $8.20 per lot) $241.50 $249.70
Water Corporation water ($2,756 per extra lot) $2,756.00 $5,512.00
Water Corporation wastewater ($5,121 per extra lot) $5,121.00 $10,242.00
Total published fees $13,564.50 $21,712.70

Water and wastewater contributions are the largest published items, so each extra lot adds most to the total. To run the numbers for a different number of lots, use our subdivision cost calculator.

Costs that are not in the total

Public open space. For residential subdivision, the WAPC's Position Statement: Public Open Space sets a standard of 10% of the gross subdivisible area, given as land or as cash in lieu. For infill subdivision, the contribution can default to 0% until 18 December 2027 unless the local planning scheme already requires it. From 19 December 2027, infill subdivisions of five lots or fewer are not required to contribute unless a local planning strategy or local planning scheme justifies it. Whether a contribution applies to your subdivision is set by the WAPC's conditions of approval.

Quoted work. These have no official figure and are priced on your site:

  • the licensed surveyor's survey and plan of subdivision
  • a town planner's report, if the application needs one
  • specialist reports such as bushfire, heritage, geotechnical or contamination
  • water, sewer, drainage, power and telecommunications connections, and any main extensions
  • demolition or relocation of buildings that sit across the new boundary, and crossovers and driveways
  • conveyancing or legal work

Early checks. A Basic Summary of Records (Form 2) from the Department of Water and Environmental Regulation, which covers reported contaminated sites that are not listed online, is $44.

Where sewer is not available or mains need extending, the cost of works can rise sharply. That is one of the first things to check for your block.

Rules that come first

Whether your block can be split at all depends first on its R-Code and area. Our WA minimum lot size guide explains the minimum and average site area tests, and our guide to subdividing in WA walks through the full process. For local rules, see our council guides for Stirling, Wanneroo, Joondalup, Swan, Gosnells, Cockburn and Melville. For how the costs compare across Australia, see how much it costs to subdivide in Australia.

A licensed surveyor or town planner can confirm what your subdivision will involve and quote the work.

Frequently asked questions

How much does it cost to subdivide a block into two lots in WA?

The government fees and Water Corporation contributions for a two-lot green-title or survey-strata split add up to $13,564.50 from 1 July 2026, if the council charges the maximum clearance fee, the existing lot is already connected to water and sewer, and Water Corporation contributions are charged on the extra lot only. Surveying, planning reports, service connections, demolition and other works are quoted on scope and usually add much more.

What is the WAPC subdivision application fee in 2026?

From 1 July 2026, under the Planning and Development (Fees) Amendment Notice 2026, the WAPC fee for a freehold, survey-strata or community titles subdivision of 100 lots or fewer is $3,837 plus $85 per lot. That is $4,007 for two lots. Endorsement of the final plan is $719 plus $8 per lot, or $735 for two lots.

What are Water Corporation's subdivision charges in 2026-27?

Water Corporation's infrastructure contributions for 1 July 2026 to 30 June 2027 are $2,756 for water and $5,121 for wastewater per lot, plus $41 for drainage on green-title lots in urban declared drainage areas of metropolitan Perth. They are payable when a subdivision creates extra lots that need Water Corporation's services; Water Corporation confirms how many lots are charged and the amount for your subdivision.

Does the council charge a fee to clear subdivision conditions in WA?

Yes. Schedule 2 of the Planning and Development Regulations 2009 sets a maximum of $73 per lot for the local government's subdivision clearance where no more than five lots are created. Councils can charge less.

Sources

This guide is general information only, current at 18 November 2026. Fees change, usually on 1 July. Speak to a licensed surveyor or town planner about your property.